Benchmark Data

Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 422,674,944.85 4,693.30 50,518.66 -
MEP % of Total Project Sum 44% - - -
Total Project Sum 991,018,777.78 11,004.07 118,447.86 -
Floor Area (M²) 90,059.26 - - -
MEP Sum Per M² 4,808.28 - - -
MW Size 79.30 - - -
MEP Sum Per MW 5,457,007.67 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 104,491,457.31 1,160.25 12,488.96 -
Preliminaries 15% 47,727,589.82 529.96 5,704.46
11.29%
Design & Professional Fees 3% 9,545,571.32 105.99 1,140.90
2.26%
Risk/Contingency 5% 15,909,241.07 176.65 1,901.49
3.76%
OH&P 8% 31,309,321.86 347.65 3,742.13
7.41%
Inflation 90.80 0.00 0.01
0.00%
Mechanical Total → 83,209,802.95 923.95 9,945.34 -
Chillers 14,655,790.97 162.73 1,751.68
3.47%
Dry Air Coolers 4,001,465.10 44.43 478.26
0.95%
Fan Wall Units 8,051,073.12 89.40 962.27
1.90%
CRAH 1,349,936.03 14.99 161.35
0.32%
CRAC 723,210.98 8.03 86.44
0.17%
Packaged Pump Rooms 6,026,269.11 66.91 720.27
1.43%
Plant Movement/Handling (Mech) 916,049.46 10.17 109.49
0.22%
General Mechanical 28,588,370.95 317.44 3,416.92
6.76%
BMS/BAS/EMS/PMS/EPMS 6,460,155.68 71.73 772.13
1.53%
Fire Protection Suppression System 8,147,492.36 90.47 973.80
1.93%
Commissioning Management 1,447,102.52 16.07 172.96
0.34%
Mechanical Abnormals 2,842,964.65 31.57 339.79
0.67%
Electrical Total → 234,973,684.59 2,609.10 28,084.36 -
Generators & Fuel Tanks 40,158,679.59 445.91 4,799.82
9.50%
Packaged Equipment Rooms 5,399,544.06 59.96 645.36
1.28%
Substation RMU Transformers 8,051,073.12 89.40 962.27
1.90%
UPS Battery 21,356,928.05 237.14 2,552.61
5.05%
MV LV Switchgear Panelboards 10,702,602.18 118.84 1,279.19
2.53%
Plant Movement/Handling (Elec) 1,976,661.08 21.95 236.25
0.47%
General Electrical 125,730,753.89 1,396.09 15,027.50
29.75%
Security Systems 3,326,530.43 36.94 397.59
0.79%
ICT Communications TV Data 4,724,609.38 52.46 564.69
1.12%
Fire Detection Alarm 2,603,386.13 28.91 311.16
0.62%
Photovoltaic Solar 4,821,028.62 53.53 576.22
1.14%
Lightning Protection 1,349,936.03 14.99 161.35
0.32%
Load Banking Testing 2,169,499.56 24.09 259.30
0.51%
Electrical Abnormals 2,602,041.07 28.89 311.00
0.62%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 40,351,703.56 2,864.47 30,833.19 -
MEP % of Total Project Sum 27% - - -
Total Project Sum 151,318,888.34 10,741.77 115,624.44 -
Floor Area (M²) 14,086.96 - - -
MEP Sum Per M² 2,790.77 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 7,888,547.03 559.99 6,027.73 -
Preliminaries 15% 3,246,315.65 230.45 2,480.55
8.05%
Design & Professional Fees 3% 324,631.57 23.04 248.05
0.80%
Risk/Contingency 5% 649,263.13 46.09 496.11
1.61%
OH&P 8% 3,668,336.69 260.41 2,803.02
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 18,964,625.09 1,346.25 14,491.08 -
Boilers 877,382.61 62.28 670.42
2.17%
Pumps & Booster Sets 1,048,472.22 74.43 801.15
2.60%
Chillers and Water Coolers / Towers 2,316,290.09 164.43 1,769.90
5.74%
Air Handling Units 1,509,098.09 107.13 1,153.12
3.74%
Air Source Heat Pumps / Ground Source Heat Pumps 754,549.04 53.56 576.56
1.87%
CHP Units / Other District Heating Plant 601,007.09 42.66 459.24
1.49%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 1,921,467.91 136.40 1,468.21
4.76%
Sanitaryware 622,941.65 44.22 476.00
1.54%
Electric Heaters 166,702.70 11.83 127.38
0.41%
Rainwater Harvesting 197,411.09 14.01 150.84
0.49%
Other Misc Plant 271,988.61 19.31 207.83
0.67%
Mech Plant Movement/Handling 144,768.13 10.28 110.62
0.36%
Mechanical Incoming External Services / Mains (Gas & Water) 478,173.52 33.94 365.38
1.19%
Incoming Sprinkler Mains & Hydrants 250,054.04 17.75 191.07
0.62%
General Mechanical (Pipework, Drainage, Brackets, Valves) 2,092,557.52 148.55 1,598.95
5.19%
Ductwork & Ventilation 1,754,765.22 124.57 1,340.84
4.35%
Air Conditioning 890,543.35 63.22 680.47
2.21%
BMS/BAS/EMS/PMS/EPMS 631,715.48 44.84 482.70
1.57%
Fire Protection Suppression System 1,355,556.13 96.23 1,035.80
3.36%
Lifts (Physical) 407,982.91 28.96 311.74
1.01%
Commissioning Management 285,149.35 20.24 217.89
0.71%
Mechanical Abnormals 386,048.35 27.40 294.98
0.96%
Electrical Total → 13,498,531.43 958.23 10,314.38 -
Generators & Fuel Tanks 451,852.04 32.08 345.27
1.12%
Packaged Equipment Rooms 320,244.65 22.73 244.70
0.79%
Substation RMU Transformers 447,465.13 31.76 341.91
1.11%
UPS Battery 394,822.17 28.03 301.69
0.98%
MV LV Switchgear Panelboards 1,338,008.48 94.98 1,022.39
3.32%
Luminaires Light Fittings 864,221.87 61.35 660.36
2.14%
Other Misc Electrical Plant 201,798.00 14.33 154.20
0.50%
Plant Movement/Handling (Elec) 162,315.78 11.52 124.03
0.40%
Electrical Incoming External Services 614,167.83 43.60 469.29
1.52%
Electric Vehicle Suppliers Chargers 162,315.78 11.52 124.03
0.40%
Internal Submains Cabling 745,775.22 52.94 569.86
1.85%
Busbar Dedicated Power Systems 350,953.04 24.91 268.17
0.87%
General Electrical 3,948,221.74 280.28 3,016.88
9.78%
Lighting Luminaires 500,108.09 35.50 382.14
1.24%
CCTV Access Control Security 552,751.04 39.24 422.36
1.37%
ICT Communications TV Data 469,399.70 33.32 358.67
1.16%
Powered Blinds 184,250.35 13.08 140.79
0.46%
Nurse Call Specialist Systems 144,768.13 10.28 110.62
0.36%
Fire Detection Alarm 960,733.96 68.20 734.11
2.38%
Photovoltaic Solar 144,768.13 10.28 110.62
0.36%
Lightning Protection 188,637.26 13.39 144.14
0.47%
Lift Power Supply Only 21,934.57 1.56 16.76
0.05%
Testing 122,833.57 8.72 93.86
0.30%
Electrical Abnormals 206,184.91 14.64 157.55
0.51%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 25,148,234.89 1,369.08 14,736.78 -
MEP % of Total Project Sum 27% - - -
Total Project Sum 94,305,880.84 5,134.05 55,262.91 -
Floor Area (M²) 18,368.71 - - -
MEP Sum Per M² 1,414.25 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 4,916,348.42 267.65 2,880.96 -
Preliminaries 15% 2,023,188.65 110.14 1,185.58
8.05%
Design & Professional Fees 3% 202,318.87 11.01 118.56
0.80%
Risk/Contingency 5% 404,637.73 22.03 237.12
1.61%
OH&P 8% 2,286,203.17 124.46 1,339.71
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 12,405,060.57 675.34 7,269.32 -
Boilers 455,800.68 24.81 267.10
1.81%
Pumps & Booster Sets 728,202.27 39.64 426.72
2.90%
Chillers and Water Coolers / Towers 329,039.55 17.91 192.82
1.31%
Air Handling Units 291,280.91 15.86 170.69
1.16%
Air Source Heat Pumps / Ground Source Heat Pumps 1,310,764.09 71.36 768.10
5.21%
CHP Units / Other District Heating Plant 728,202.27 39.64 426.72
2.90%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 1,092,303.41 59.47 640.09
4.34%
Sanitaryware 911,601.36 49.63 534.20
3.62%
Electric Heaters 91,699.55 4.99 53.74
0.36%
Rainwater Harvesting 126,761.14 6.90 74.28
0.50%
Other Misc Plant 110,578.86 6.02 64.80
0.44%
Mech Plant Movement/Handling 91,699.55 4.99 53.74
0.36%
Mechanical Incoming External Services / Mains (Gas & Water) 364,101.14 19.82 213.36
1.45%
Incoming Sprinkler Mains & Hydrants 196,884.32 10.72 115.37
0.78%
General Mechanical (Pipework, Drainage, Brackets, Valves) 1,658,682.95 90.30 971.98
6.60%
Ductwork & Ventilation 1,022,180.23 55.65 598.99
4.06%
Air Conditioning 547,500.23 29.81 320.83
2.18%
BMS/BAS/EMS/PMS/EPMS 364,101.14 19.82 213.36
1.45%
Fire Protection Suppression System 728,202.27 39.64 426.72
2.90%
Lifts (Physical) 821,250.34 44.71 481.25
3.27%
Commissioning Management 218,460.68 11.89 128.02
0.87%
Mechanical Abnormals 215,763.64 11.75 126.44
0.86%
Electrical Total → 7,826,825.91 426.10 4,586.49 -
Generators & Fuel Tanks 129,458.18 7.05 75.86
0.51%
Packaged Equipment Rooms 129,458.18 7.05 75.86
0.51%
Substation RMU Transformers 323,645.45 17.62 189.66
1.29%
UPS Battery 26,970.45 1.47 15.80
0.11%
MV LV Switchgear Panelboards 701,231.82 38.18 410.92
2.79%
Luminaires Light Fittings 647,290.91 35.24 379.31
2.57%
Other Misc Electrical Plant 78,214.32 4.26 45.83
0.31%
Plant Movement/Handling (Elec) 64,729.09 3.52 37.93
0.26%
Electrical Incoming External Services 323,645.45 17.62 189.66
1.29%
Electric Vehicle Suppliers Chargers 347,918.86 18.94 203.88
1.38%
Internal Submains Cabling 585,258.86 31.86 342.96
2.33%
Busbar Dedicated Power Systems 258,916.36 14.10 151.72
1.03%
General Electrical 1,696,441.59 92.35 994.11
6.75%
Lighting Luminaires 544,803.18 29.66 319.25
2.17%
CCTV Access Control Security 517,832.73 28.19 303.45
2.06%
ICT Communications TV Data 323,645.45 17.62 189.66
1.29%
Powered Blinds 221,157.73 12.04 129.60
0.88%
Nurse Call Specialist Systems 0.00 0.00 0.00
0.00%
Fire Detection Alarm 453,103.64 24.67 265.52
1.80%
Photovoltaic Solar 151,034.55 8.22 88.51
0.60%
Lightning Protection 124,064.09 6.75 72.70
0.49%
Lift Power Supply Only 18,879.32 1.03 11.06
0.08%
Testing 64,729.09 3.52 37.93
0.26%
Electrical Abnormals 94,396.59 5.14 55.32
0.38%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 14,331,550.57 268.75 2,892.82 -
MEP % of Total Project Sum 25% - - -
Total Project Sum 57,326,202.29 1,075.00 11,571.28 -
Floor Area (M²) 53,326.80 - - -
MEP Sum Per M² 306.29 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 2,487,293.90 46.64 502.06 -
Preliminaries 15% 829,097.97 15.55 167.35
5.79%
Design & Professional Fees 3% 118,442.57 2.22 23.91
0.83%
Risk/Contingency 5% 236,885.13 4.44 47.82
1.65%
OH&P 8% 1,302,868.23 24.43 262.98
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 4,153,180.91 77.88 838.32 -
Boilers 38,455.38 0.72 7.76
0.27%
Pumps & Booster Sets 61,528.61 1.15 12.42
0.43%
Chillers and Water Coolers / Towers 0.00 0.00 0.00
0.00%
Air Handling Units 215,350.12 4.04 43.47
1.50%
Air Source Heat Pumps / Ground Source Heat Pumps 235,346.92 4.41 47.50
1.64%
CHP Units / Other District Heating Plant 0.00 0.00 0.00
0.00%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 299,951.95 5.62 60.55
2.09%
Sanitaryware 61,528.61 1.15 12.42
0.43%
Electric Heaters 46,146.45 0.87 9.31
0.32%
Rainwater Harvesting 153,821.52 2.88 31.05
1.07%
Other Misc Plant 15,382.15 0.29 3.10
0.11%
Mech Plant Movement/Handling 23,073.23 0.43 4.66
0.16%
Mechanical Incoming External Services / Mains (Gas & Water) 186,124.03 3.49 37.57
1.30%
Incoming Sprinkler Mains & Hydrants 769,107.58 14.42 155.24
5.37%
General Mechanical (Pipework, Drainage, Brackets, Valves) 315,334.11 5.91 63.65
2.20%
Ductwork & Ventilation 502,996.36 9.43 101.53
3.51%
Air Conditioning 121,519.00 2.28 24.53
0.85%
BMS/BAS/EMS/PMS/EPMS 93,831.12 1.76 18.94
0.65%
Fire Protection Suppression System 999,839.85 18.75 201.82
6.98%
Lifts (Physical) 0.00 0.00 0.00
0.00%
Commissioning Management 12,305.72 0.23 2.48
0.09%
Mechanical Abnormals 1,538.21 0.03 0.31
0.01%
Electrical Total → 7,691,075.76 144.23 1,552.44 -
Generators & Fuel Tanks 99,983.98 1.87 20.18
0.70%
Packaged Equipment Rooms 167,665.45 3.14 33.84
1.17%
Substation RMU Transformers 1,076,750.61 20.19 217.34
7.51%
UPS Battery 133,824.72 2.51 27.01
0.93%
MV LV Switchgear Panelboards 976,766.62 18.32 197.16
6.82%
Luminaires Light Fittings 502,996.36 9.43 101.53
3.51%
Other Misc Electrical Plant 61,528.61 1.15 12.42
0.43%
Plant Movement/Handling (Elec) 30,764.30 0.58 6.21
0.21%
Electrical Incoming External Services 836,789.04 15.69 168.91
5.84%
Electric Vehicle Suppliers Chargers 167,665.45 3.14 33.84
1.17%
Internal Submains Cabling 538,375.30 10.10 108.67
3.76%
Busbar Dedicated Power Systems 367,633.42 6.89 74.21
2.57%
General Electrical 870,629.78 16.33 175.74
6.07%
Lighting Luminaires 678,352.88 12.72 136.93
4.73%
CCTV Access Control Security 301,490.17 5.65 60.86
2.10%
ICT Communications TV Data 133,824.72 2.51 27.01
0.93%
Powered Blinds 0.00 0.00 0.00
0.00%
Nurse Call Specialist Systems 0.00 0.00 0.00
0.00%
Fire Detection Alarm 267,649.44 5.02 54.02
1.87%
Photovoltaic Solar 292,260.88 5.48 58.99
2.04%
Lightning Protection 69,219.68 1.30 13.97
0.48%
Lift Power Supply Only 15,382.15 0.29 3.10
0.11%
Testing 38,455.38 0.72 7.76
0.27%
Electrical Abnormals 63,066.82 1.18 12.73
0.44%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 67,700,440.94 1,269.54 13,665.32 -
MEP % of Total Project Sum 29% - - -
Total Project Sum 236,951,543.30 4,443.39 47,828.60 -
Floor Area (M²) 53,326.80 - - -
MEP Sum Per M² 1,446.89 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 13,235,082.18 248.19 2,671.50 -
Preliminaries 15% 5,446,535.88 102.14 1,099.38
8.05%
Design & Professional Fees 3% 544,653.59 10.21 109.94
0.80%
Risk/Contingency 5% 1,089,307.18 20.43 219.88
1.61%
OH&P 8% 6,154,585.54 115.41 1,242.30
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 19,098,242.68 358.14 3,854.98 -
Boilers 176,835.58 3.32 35.69
0.26%
Pumps & Booster Sets 282,936.93 5.31 57.11
0.42%
Chillers and Water Coolers / Towers 0.00 0.00 0.00
0.00%
Air Handling Units 990,279.25 18.57 199.89
1.46%
Air Source Heat Pumps / Ground Source Heat Pumps 1,082,233.75 20.29 218.45
1.60%
CHP Units / Other District Heating Plant 0.00 0.00 0.00
0.00%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 1,379,317.53 25.87 278.41
2.04%
Sanitaryware 282,936.93 5.31 57.11
0.42%
Electric Heaters 212,202.70 3.98 42.83
0.31%
Rainwater Harvesting 707,342.32 13.26 142.78
1.04%
Other Misc Plant 70,734.23 1.33 14.28
0.10%
Mech Plant Movement/Handling 106,101.35 1.99 21.42
0.16%
Mechanical Incoming External Services / Mains (Gas & Water) 855,884.21 16.05 172.76
1.26%
Incoming Sprinkler Mains & Hydrants 3,536,711.61 66.32 713.88
5.22%
General Mechanical (Pipework, Drainage, Brackets, Valves) 1,450,051.76 27.19 292.69
2.14%
Ductwork & Ventilation 2,313,009.39 43.37 466.88
3.42%
Air Conditioning 558,800.43 10.48 112.79
0.83%
BMS/BAS/EMS/PMS/EPMS 431,478.82 8.09 87.09
0.64%
Fire Protection Suppression System 4,597,725.09 86.22 928.05
6.79%
Lifts (Physical) 0.00 0.00 0.00
0.00%
Commissioning Management 56,587.39 1.06 11.42
0.08%
Mechanical Abnormals 7,073.42 0.13 1.43
0.01%
Electrical Total → 35,367,116.08 663.21 7,138.84 -
Generators & Fuel Tanks 459,772.51 8.62 92.80
0.68%
Packaged Equipment Rooms 771,003.13 14.46 155.63
1.14%
Substation RMU Transformers 4,951,396.25 92.85 999.44
7.31%
UPS Battery 615,387.82 11.54 124.22
0.91%
MV LV Switchgear Panelboards 4,491,623.74 84.23 906.63
6.63%
Luminaires Light Fittings 2,313,009.39 43.37 466.88
3.42%
Other Misc Electrical Plant 282,936.93 5.31 57.11
0.42%
Plant Movement/Handling (Elec) 141,468.46 2.65 28.56
0.21%
Electrical Incoming External Services 3,847,942.23 72.16 776.71
5.68%
Electric Vehicle Suppliers Chargers 771,003.13 14.46 155.63
1.14%
Internal Submains Cabling 2,475,698.12 46.43 499.72
3.66%
Busbar Dedicated Power Systems 1,690,548.15 31.70 341.24
2.50%
General Electrical 4,003,557.54 75.08 808.12
5.91%
Lighting Luminaires 3,119,379.64 58.50 629.65
4.61%
CCTV Access Control Security 1,386,390.95 26.00 279.84
2.05%
ICT Communications TV Data 615,387.82 11.54 124.22
0.91%
Powered Blinds 0.00 0.00 0.00
0.00%
Nurse Call Specialist Systems 0.00 0.00 0.00
0.00%
Fire Detection Alarm 1,230,775.64 23.08 248.43
1.82%
Photovoltaic Solar 1,343,950.41 25.20 271.28
1.99%
Lightning Protection 318,304.04 5.97 64.25
0.47%
Lift Power Supply Only 70,734.23 1.33 14.28
0.10%
Testing 176,835.58 3.32 35.69
0.26%
Electrical Abnormals 290,010.35 5.44 58.54
0.43%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 53,311,895.88 999.72 10,760.99 -
MEP % of Total Project Sum 32% - - -
Total Project Sum 167,932,472.02 3,149.12 33,897.12 -
Floor Area (M²) 53,326.80 - - -
MEP Sum Per M² 1,139.31 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 10,422,196.86 195.44 2,103.72 -
Preliminaries 15% 4,288,969.90 80.43 865.73
8.05%
Design & Professional Fees 3% 428,896.99 8.04 86.57
0.80%
Risk/Contingency 5% 857,793.98 16.09 173.15
1.61%
OH&P 8% 4,846,535.99 90.88 978.27
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 31,172,497.25 584.56 6,292.16 -
Boilers 209,985.35 3.94 42.39
0.39%
Pumps & Booster Sets 335,976.55 6.30 67.82
0.63%
Chillers and Water Coolers / Towers 0.00 0.00 0.00
0.00%
Air Handling Units 1,175,917.94 22.05 237.36
2.21%
Air Source Heat Pumps / Ground Source Heat Pumps 1,285,110.32 24.10 259.40
2.41%
CHP Units / Other District Heating Plant 0.00 0.00 0.00
0.00%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 3,275,771.40 61.43 661.21
6.14%
Sanitaryware 439,823.85 8.25 88.78
0.83%
Electric Heaters 251,982.42 4.73 50.86
0.47%
Rainwater Harvesting 839,941.38 15.75 169.54
1.58%
Other Misc Plant 83,994.14 1.58 16.95
0.16%
Mech Plant Movement/Handling 125,991.21 2.36 25.43
0.24%
Mechanical Incoming External Services / Mains (Gas & Water) 1,016,329.07 19.06 205.15
1.91%
Incoming Sprinkler Mains & Hydrants 4,199,706.92 78.75 847.71
7.88%
General Mechanical (Pipework, Drainage, Brackets, Valves) 1,721,879.84 32.29 347.56
3.23%
Ductwork & Ventilation 3,995,066.66 74.92 806.40
7.49%
Air Conditioning 1,085,815.13 20.36 219.17
2.04%
BMS/BAS/EMS/PMS/EPMS 819,782.79 15.37 165.47
1.54%
Fire Protection Suppression System 7,941,264.00 148.92 1,602.94
14.90%
Lifts (Physical) 2,292,563.56 42.99 462.75
4.30%
Commissioning Management 67,195.31 1.26 13.56
0.13%
Mechanical Abnormals 8,399.41 0.16 1.70
0.02%
Electrical Total → 11,717,201.77 219.72 2,365.11 -
Generators & Fuel Tanks 121,255.58 2.27 24.48
0.23%
Packaged Equipment Rooms 203,336.28 3.81 41.04
0.38%
Substation RMU Transformers 2,374,235.09 44.52 479.24
4.45%
UPS Battery 472,133.61 8.85 95.30
0.89%
MV LV Switchgear Panelboards 1,593,790.10 29.89 321.71
2.99%
Luminaires Light Fittings 427,006.18 8.01 86.19
0.80%
Other Misc Electrical Plant 74,618.82 1.40 15.06
0.14%
Plant Movement/Handling (Elec) 37,309.41 0.70 7.53
0.07%
Electrical Incoming External Services 1,014,815.91 19.03 204.84
1.90%
Electric Vehicle Suppliers Chargers 189,125.35 3.55 38.17
0.35%
Internal Submains Cabling 1,187,117.54 22.26 239.62
2.23%
Busbar Dedicated Power Systems 445,847.43 8.36 89.99
0.84%
General Electrical 1,055,856.26 19.80 213.12
1.98%
Lighting Luminaires 822,672.46 15.43 166.06
1.54%
CCTV Access Control Security 365,632.20 6.86 73.80
0.69%
ICT Communications TV Data 162,295.93 3.04 32.76
0.30%
Powered Blinds 204,492.87 3.83 41.28
0.38%
Nurse Call Specialist Systems 0.00 0.00 0.00
0.00%
Fire Detection Alarm 324,591.85 6.09 65.52
0.61%
Photovoltaic Solar 354,439.38 6.65 71.54
0.66%
Lightning Protection 98,217.02 1.84 19.83
0.18%
Lift Power Supply Only 18,654.70 0.35 3.77
0.03%
Testing 93,273.52 1.75 18.83
0.17%
Electrical Abnormals 76,484.29 1.43 15.44
0.14%
Category Average £/M² £/Sq. Ft. % / Vote Higher or Lower
Total MEP Value → 118,838,963.65 2,228.50 23,987.61 -
MEP % of Total Project Sum 32% - - -
Total Project Sum 374,342,735.50 7,019.79 75,560.98 -
Floor Area (M²) 53,326.80 - - -
MEP Sum Per M² 2,539.82 - - -
MW Size 0.00 - - -
MEP Sum Per MW 0.00 - - -
Prelims, Fees, Contingency, OH&P, Inflation → 25,301,802.18 474.47 5,107.16 -
Preliminaries 15% 11,692,145.18 219.25 2,360.06
9.84%
Design & Professional Fees 3% 935,371.61 17.54 188.80
0.79%
Risk/Contingency 5% 1,870,743.23 35.08 377.61
1.57%
OH&P 8% 10,803,542.15 202.59 2,180.69
9.09%
Inflation 0.00 0.00 0.00
0.00%
Mechanical Total → 56,371,885.75 1,057.10 11,378.65 -
Boilers 1,854,263.94 34.77 374.28
1.56%
Pumps & Booster Sets 890,046.69 16.69 179.66
0.75%
Chillers and Water Coolers / Towers 2,865,950.34 53.74 578.49
2.41%
Air Handling Units 5,295,777.80 99.31 1,068.95
4.46%
Air Source Heat Pumps / Ground Source Heat Pumps 1,702,214.29 31.92 343.59
1.43%
CHP Units / Other District Heating Plant 0.00 0.00 0.00
0.00%
Air Conditioning Equipment, Condensers, FCU's, CRF Units 5,062,140.55 94.93 1,021.79
4.26%
Sanitaryware 88,498.96 1.66 17.86
0.07%
Electric Heaters 289,728.74 5.43 58.48
0.24%
Rainwater Harvesting 482,881.23 9.06 97.47
0.41%
Other Misc Plant 556,279.18 10.43 112.28
0.47%
Mech Plant Movement/Handling 278,139.59 5.22 56.14
0.23%
Mechanical Incoming External Services / Mains (Gas & Water) 529,164.95 9.92 106.81
0.45%
Incoming Sprinkler Mains & Hydrants 965,762.47 18.11 194.94
0.81%
General Mechanical (Pipework, Drainage, Brackets, Valves) 6,081,985.72 114.05 1,227.65
5.12%
Ductwork & Ventilation 14,111,285.70 264.62 2,848.36
11.87%
Air Conditioning 2,397,057.56 44.95 483.85
2.02%
BMS/BAS/EMS/PMS/EPMS 1,809,761.60 33.94 365.30
1.52%
Fire Protection Suppression System 10,518,733.61 197.25 2,123.20
8.85%
Lifts (Physical) 0.00 0.00 0.00
0.00%
Commissioning Management 364,438.67 6.83 73.56
0.31%
Mechanical Abnormals 227,774.17 4.27 45.98
0.19%
Electrical Total → 37,165,275.72 696.93 7,501.80 -
Generators & Fuel Tanks 1,687,380.18 31.64 340.60
1.42%
Packaged Equipment Rooms 2,829,606.77 53.06 571.16
2.38%
Substation RMU Transformers 3,072,880.58 57.62 620.26
2.59%
UPS Battery 1,833,192.76 34.38 370.03
1.54%
MV LV Switchgear Panelboards 8,251,123.33 154.73 1,665.49
6.94%
Luminaires Light Fittings 1,894,825.96 35.53 382.47
1.59%
Other Misc Electrical Plant 741,705.58 13.91 149.71
0.62%
Plant Movement/Handling (Elec) 437,326.40 8.20 88.27
0.37%
Electrical Incoming External Services 826,060.98 15.49 166.74
0.70%
Electric Vehicle Suppliers Chargers 108,337.68 2.03 21.87
0.09%
Internal Submains Cabling 2,782,986.18 52.19 561.75
2.34%
Busbar Dedicated Power Systems 2,090,420.19 39.20 421.95
1.76%
General Electrical 2,475,267.42 46.42 499.63
2.08%
Lighting Luminaires 1,928,609.43 36.17 389.29
1.62%
CCTV Access Control Security 1,371,455.59 25.72 276.83
1.15%
ICT Communications TV Data 1,826,275.05 34.25 368.63
1.54%
Powered Blinds 0.00 0.00 0.00
0.00%
Nurse Call Specialist Systems 0.00 0.00 0.00
0.00%
Fire Detection Alarm 1,217,516.70 22.83 245.76
1.02%
Photovoltaic Solar 432,770.92 8.12 87.35
0.36%
Lightning Protection 196,796.88 3.69 39.72
0.17%
Lift Power Supply Only 22,777.42 0.43 4.60
0.02%
Testing 241,440.62 4.53 48.73
0.20%
Electrical Abnormals 896,519.12 16.81 180.96
0.75%

This is a public view of benchmark data. You can vote on values.